Summary
Almost all of Girdwood's gas comes through one 6-inch plastic main that runs from Enstar's regulator station on Ruane Road up the Alyeska Highway.3 If that main is cut, everyone downstream of the break loses gas. Enstar wants to add a second, 4-inch line from the end of Ruane Road, under Glacier Creek, to Virgin Creek Road, so gas can reach the valley from both ends (a "two-way feed").5,9▸49:04
In its 2023 application to DNR, Enstar placed the whole line inside a state section-line easement that runs east–west across Heritage Land Bank land. The plan was 4,850 feet of 4-inch pipe: 1,650 feet drilled underground (mostly a 1,500-foot bore under Glacier Creek and its wetlands), and 3,350 feet in a trench, in a 20-foot-wide strip cleared west from the end of Virgin Creek Road.25p.5 In the 2023 plan, the cleared strip would run through old-growth forest and cross two trails, the Lower Virgin Creek Trail and the Joe Danich Trail.4,29p.4 The line would not cross Virgin Creek itself.29p.1 Residents and the Girdwood Board of Supervisors (GBOS) objected in 2023. The state Department of Natural Resources (DNR) decided in August 2024 to issue a letter of non-objection. Neighbors appealed, DNR's Commissioner denied the appeal in June 2025, and DNR issued the letter on June 20, 2025.29p.4,8,33
HLB Resolution 2026-11 proposes a change in the routing of the originally proposed gas line. It would grant Enstar a permanent, non-exclusive gas easement plus a temporary construction easement on part of Heritage Land Bank Parcel 6-062 (Tract 20-A). HLB calls it an alternative route for a project that would otherwise be built in the section-line easement.1 The easement's legal description shows what changes: a 20-foot strip about 1,000 feet long that leaves the section-line easement about 980 feet west of the parcel's northeast corner and runs diagonally to the west end of Virgin Creek Road, plus a 65 × 75 foot work area beside the road.14p.64 GBOS's agenda describes it as letting the gas line "be angled to intersect with Virgin Creek Road."32 In the 2023 plan, the east end stayed on the section line and then turned south to the road (approximate on the map). The rest of the line, including the bore under Glacier Creek, still starts in the section-line easement.
This is why HLB is involved now. The section-line easement is a state right, so building inside it needed DNR's approval, not HLB's. The rerouted east end leaves that easement and crosses land HLB owns outright, so Enstar needs an easement from HLB for that stretch.1,29p.15 See Why is HLB involved now? for details.
Timeline
- Background
Gas service reaches Girdwood
Through a single 6-inch main up the Alyeska Highway.3
Contractor hits the Girdwood main
A Granite Construction crew working on a DOT road project near 1127 Alyeska Hwy damaged the top of the 6-inch main. Pressure fell from over 50 psi to 5 psi. Service held thanks to low summer demand, Hotel Alyeska switching to backup fuel, and a quick bypass. Enstar says that otherwise about 1,000 homes and businesses would have lost gas.3
Ruane Road washout exposes a gas line
Heavy rain exposed a 2-inch main feeding the wastewater plant. It was cut out, replaced and bypassed.3
- 2023: the section-line plan
Enstar applies to DNR to build the line in the section-line easement (ADL 234206)
To build 4,850 ft of 4-inch main within the section-line easement, with 3–4 weeks of construction planned for late July to early September 2023.25p.2,29p.1 Enstar says HLB was notified in spring 2023.27 DNR treated its public notice of the application as a "courtesy," not one required by law.29p.8
Enstar presents the gas line to GBOS; GBOS votes 4–0 to object
About 90 minutes of questions and public comment, mostly opposed. The motion was to send DNR a letter objecting to the project itself, and board members amended it to also ask for a 30-day extension of the comment period. In discussion, board members said the community had learned of the plan too late, and some questioned whether the line was needed.9▸1:58:24▸2:08:38,28 Watch the presentation
GBOS sends DNR its letter objecting to the gas line
The letter asks DNR to extend the comment period to Aug 21 and to deny Enstar's application because of the clearcut across community trails.4
DNR's comment period closes; Enstar replies to GBOS
On July 19, DNR extended the deadline to Aug 3 and posted notices in Girdwood. DNR received 27 public comments in total.24,29p.8 On Aug 3, Enstar wrote to GBOS explaining why it says Girdwood needs a second feed (a break on the single main could leave the valley without gas for days) and saying "further review and dialogue" were warranted.3
- 2024: approval and appeal
DNR clears Enstar to build in the section-line easement
DNR concluded that a gas main is "an acceptable secondary use" of the section-line easement. It issued a letter of non-objection with no stipulations. Cost, alternative routes, viewsheds and gas supply were all ruled outside the decision's scope. DNR also noted that Enstar no longer expects to need to cross Virgin Creek.29p.1 DNR's case file dates the decision Aug 28 and records that the permit signature was withheld until Sept 18, pending the appeal period.33
Land Use Committee backs neighbors' planned appeal of DNR's decision
The committee recommended that GBOS support the appeal Brenden Raymond-Yakoubian was preparing against DNR's Aug 26 decision. He lives on Virgin Creek Road, and in 2023 he told GBOS the route would run through the open space in front of his house and through an easement on his property.9▸1:05:35 It also noted that Enstar hadn't answered requests to consider another alignment.12
Enstar puts the gas line on hold pending any appeal
Enstar told GBOS it would make no final decision on the gas line until any appeal of DNR's decision was resolved, and expected no construction in 2024.30
GBOS declines to back the neighbors' planned appeal
A motion for GBOS to file its own appeal of DNR's decision failed 0–4 after staff said service-area money can't fund an appeal. A letter of concern to Enstar and a letter supporting the residents' planned appeal each failed 2–2.10▸13:18▸1:08:04▸1:08:52,11 Watch the votes
Neighbors appeal DNR's decision to the DNR Commissioner
Brenden Raymond-Yakoubian and other residents appealed DNR's Aug 26 decision allowing the gas line in the section-line easement. Turnagain News reported two other residents; DNR's case file records the appeal as received Sept 16 from Raymond-Yakoubian "and 3 others."8,33 Appeals were due within 20 calendar days of the decision,29p.4 and at the Sep 13 meeting the GBOS chair put the deadline at Tuesday, Sep 17.10▸7:20
- 2025–2026
DNR Commissioner denies the neighbors' appeal; DNR issues the letter of non-objection
DNR's case file records a Commissioner's decision dated June 18, 2025 that "denies B. Raymond-Yakoubian's appeal." On June 20, DNR issued the letter of non-objection "for use of section line easement on land parcels owned by Anch. Muni. Heritage Land Bank" and marked the case approved.33
Whittier loses gas for a week
A submerged section of the single 8-inch line under the Twentymile River broke. Enstar shut off Whittier on Aug 16 and restored it by Aug 23 using trucked-in LNG. Enstar said the lack of redundancy there is one reason it has pursued the "Girdwood Reinforcement Pipeline."16,17,18
Mayor and Assembly
HLBAC's recommendation goes to the Mayor and Assembly, which decide disposals of HLB land.15
Questions and answers
Each answer is labeled by how solid it is: Documented means a public record says so. Estimate is rough arithmetic from those records, done for this page. Not public means no public answer turned up, so it is a good question to ask on Nov 19.
What is the line for? Is it only redundancy?
Documented Enstar's stated purpose is reliability. Adding a second feed means that a break on the existing main doesn't cut off everyone downstream. Enstar calls Girdwood "a prime example" of an area that needs this. In 2022 it built over 40,000 feet of main elsewhere to give other single-feed areas a second feed.3
Growth is part of the reason too. In written answers to GBOS in July 2023, Enstar said that "as the Girdwood community continues to expand and demand for natural gas grows," more load falls on the single feed.27 Enstar's letter says the Nordic Spa at Hotel Alyeska added "significant additional load," and customers on the main grew 7% from 2016 to 2023.3 The GBOS minutes record the purpose as ensuring reliability and improving "low flow of gas to some parts of the valley."28 Enstar also calls two-way feeds an industry best practice for keeping pressure high enough at the end of the line in winter.29p.17
Enstar has also said the line would help keep pressure up, which matters most in cold weather when demand peaks.16 At the July 2023 meeting, Enstar's engineer said growth and added load on the system were part of why the project had "come to a head." When explaining why a more northern route would work less well, he noted it wouldn't add capacity for "future expansion."9▸1:24:17▸1:45:54 A resident who called DNR reported being told the reasons were low gas pressure in that area and future development.9▸1:33:04 So redundancy is the main stated goal, but capacity for growth and pressure at the far ends of the system are also part of it.
Enstar's answer at GBOS (48:02) · engineer on history and load (1:23:02) · engineer on route and expansion (1:45:14)
How likely is the main line to fail, and how long would a fix take?
How a line "goes out." Documented Nationally, excavation damage is a leading cause of life-threatening pipeline incidents.20 Enstar says excavators hit its pipes "over 100 times" across its system most years, and that 45% of hits from 2016 to 2022 happened between October and March. It also lists earthquakes, leaks and washouts.3 Girdwood's own record shows two kinds: a contractor strike in 2016 and a flood washout in 2021.3 Whittier's 2026 outage came from a submerged river crossing that was exposed and moving in the current.16
Probability. Not public Enstar hasn't published a failure probability for the Girdwood main. The one documented hit on the 6-inch main since 1996 is the 2016 contractor strike, and service held through it.3
Estimate The calculations below were made by the author, who is not a pipeline engineer, from the few numbers Enstar has made public. They rest on one incident and on guesses about the length of the main and how hits are spread across Enstar's system. They could be off by a factor of several in either direction. They are here to show the kind of data a real estimate needs, not to give an answer.
Both methods suggest that some damage to the main within a decade is plausible. But most hits don't cause a valley-wide outage: in 2016 service held. An outage needs a break severe enough that Enstar has to shut the line off. A guess for that is well under the 28% figure, perhaps 5–15% over ten years, but there is no data behind the size of that reduction.
Better data would allow a better estimate. Enstar has the records needed to replace these guesses: its history of hits, leaks and repairs on the Girdwood main and on comparable mains, how many of its system-wide hits were on mains rather than service lines, how many led to shutting off service, and how long those outages lasted. If Enstar releases that data, the author will analyze it and update this section. Asking for it is a good question for Nov 19.
Time to fix. Documented Enstar estimates 4–7 days to restore service after a full outage, and months to reconnect some seasonal properties. The slow part is relighting: a technician has to turn each meter back on and relight the appliances.3 Enstar's engineer warned that in a cold snap, houses could freeze before crews reach them.9▸1:23:58 For comparison, Whittier was without gas from Aug 16 to Aug 23, 2026, for 39 meters, and only because Enstar trucked in LNG from Alberta.16,17,18 Girdwood has about 40 times as many meters.
How does Girdwood compare with other towns? Do most have two feeds?
Not public No statistic turned up on what fraction of towns, or of Enstar's service area, have redundant feeds. Enstar calls a secondary feed "a best practice in the gas pipeline" industry and says it builds them for areas that only have one line.3
Documented The closest example is Whittier, at the end of the same Turnagain Arm feed. After the August 2026 river-crossing break, the whole town was without gas for about a week. Enstar restored service only by trucking LNG and regasification equipment from Edmonton, and it says repair costs will be spread across all ratepayers.16 Locally, in 2026 Enstar also had to reroute a gas line at Rabbit Creek in Anchorage using horizontal directional drilling.19
Why is HLB involved now, when it wasn't in 2023?
Documented The section-line easement is a state right across land HLB owns, created by state statute.14p.64 DNR manages it and treats it as a public highway,29p.15 so Enstar's 2023 plan to build inside it needed DNR's authorization (ADL 234206), not HLB's. HLB's role was that of a landowner who could comment. Enstar says it notified HLB in spring 2023, and HLB sent DNR no comments.27,29p.9
Documented The angled east end leaves the section-line easement and crosses land HLB owns outright, with no state right over it. Building there needs an easement from HLB. An easement is a disposal of HLB land, so it goes to an HLBAC hearing and recommendation, then to the Mayor and Assembly.1,15 Res. 2026-11 covers only that strip (about 1,000 feet) and the temporary work area by the road. The rest of the line relies on DNR's 2024 decision. Neighbors appealed it, and DNR's Commissioner denied the appeal in June 2025.33
Not public In the 2023 plan, the last stretch from the section line south to the end of Virgin Creek Road also lay outside the 100-foot section-line easement. No source reviewed here says how Enstar planned to cover it, for example through the road right-of-way or a platted utility easement. DNR's figure of 2.23 acres (20 feet × 4,850 feet) suggests the application treated the whole length as one corridor.29 If that connection needed HLB's permission anyway, it may be part of why Enstar went to HLB now. HLB's staff report should say.
What other routes were considered, and how do they compare?
| Route | Who raised it | What's known |
|---|---|---|
| Section-line easement, Ruane Rd → bore under Glacier Creek → section line to Virgin Creek Rd (4,850 ft) | Enstar's 2023 application | Enstar's written answer to GBOS: "This alternative is the only option available which utilizes existing rights of way, minimizes environmental impact, and accomplishes the purpose for the project."27 DNR issued its non-objection in 2024 and didn't weigh alternatives, which it says are up to the applicant.29p.6 Residents appealed, and DNR's Commissioner denied the appeal in June 2025.7,33 It crosses two trails and designated open space.4 Enstar called it "the most reasonable way" and ranked its routing priorities as cost, then safety and access, then engineering.3 |
| The same route with its east end angled across HLB Parcel 6-062 (Res. 2026-11), 20 × ~1,000 ft from the section-line easement to Virgin Creek Rd | Enstar's application to HLB (2026) | HLB describes it as an alternative to building that segment in the section-line easement.1 Its legal description fixes the alignment.14p.64 HLB's staff report wasn't available at the time of writing, so it isn't known why Enstar asked for it or how it compares with the section-line alignment for trees, trails or neighbors. |
| North along the Karolius Drive / South Townsite alignment, then east | Brett Wilbanks and Shelly Rowton (former HLB land officer) at the July 2023 meeting | Enstar's engineer said off the top of his head that leaving the existing trunk further north keeps the single-trunk bottleneck and weakens the loop. Enstar promised a fuller answer.9▸1:44:55▸1:45:37 Enstar also said this route was unfeasible because it crosses HLB land, but Rowton said Enstar had never contacted HLB.5,6 Supporters said it could serve South Townsite and open a second exit route.9▸1:42:43▸1:54:57 The GBOS minutes describe it as following an existing utility easement to Karolius, then crossing the creek nearer the Community Center.28 Enstar says it notified HLB in spring 2023, and HLB sent DNR no comments.27,29p.9 |
| Drilling the whole length instead of trenching | Public comments to DNR | DNR said it doesn't propose other construction methods. A suggestion to narrow the clearing to 10 feet outside the drilled sections also wasn't adopted, because DNR's letter has no stipulations.29p.15 |
| A future road corridor (2011 plan for a second access road) | GBOS supervisor, July 2023 | Enstar said it would take too long and doesn't reach where its distribution system is.9▸54:25▸55:11 |
| Don't build it | Several residents | Enstar said there are no economical alternatives, and any other route would be longer than a mile.9▸1:17:36▸1:18:14 Some neighbors said they would accept the outage risk instead.9▸1:25:50▸1:49:32▸1:53:15 |
| An alternative proposed in the appeal | The appellants (2024) | Presented to the Land Use Committee as having lower impact and fitting Girdwood's comprehensive plan better. Its details weren't available.8 |
Karolius question and Enstar's reply (1:42:29) · former HLB officer (1:54:22)
Who pays, and how much would Girdwood rates go up?
Documented Enstar said it is "capitalizing the project."9▸1:22:44 For a regulated utility, that means the cost goes into its rate base and is recovered over many years through rates the Regulatory Commission of Alaska (RCA) approves for its whole system. Enstar's rate cases cover all of its customers (over 150,000).21 There is no sign of a Girdwood-only surcharge. Similarly, Enstar says the Whittier repair costs will be spread across all ratepayers.16
Not public Enstar hasn't disclosed a cost estimate. DNR said it doesn't require one and that cost and how Enstar pays are outside its decision.5,29p.5 A resident at the 2023 meeting said it would cost "millions."9▸1:59:45
Estimate For a sense of scale, assume it costs $2–5 million. A utility typically collects roughly 10–15% of a capital project's cost per year in rates (return, depreciation, taxes):
So the bill impact is likely small for everyone. If Girdwood customers paid the whole cost alone, it would be about 100 times more per customer, but nothing suggests that's how it would be billed.
Could the gas line corridor be an emergency road if the Alyeska Highway bridge is out?
Documented Not as proposed. The line would go under Glacier Creek by horizontal directional drilling, so no bridge would be built.9▸50:03 The cleared strip would be about 15–20 feet wide, reseeded, and left for alders to grow back.9▸1:03:01▸1:04:17 When asked in 2023 about pairing the work with a second access road, Enstar said that plan didn't fit its timeline or its system.9▸54:25▸55:11
That said, the section-line easement itself is 100 feet wide, and its primary legal purpose is public highway access. DNR noted that it "can be developed" as a road under state law.29p.7 So the gas line doesn't create a road, but it wouldn't rule one out in the same easement. A road would need its own bridge over Glacier Creek, design, funding and permits.
Will the public be able to use the gas line corridor afterward? For what?
Documented Enstar said it can't speak to future uses. It would restore the land as its permits require, mulching cleared brush on site and reseeding.9▸1:01:23 Its engineer said he didn't know whether people would start using it as a trail.9▸1:04:25 The section-line easement itself is a public access easement, and the state says such easements are "reserved for public use" and can't be obstructed.22 DNR said construction would temporarily block access to the Lower Virgin Creek, Joe Danich and Lower Iditarod trails, but not permanently. It also said none of these trails are legally protected rights-of-way.29p.4p.11 During construction, ADF&G asked that anglers' access to Glacier and California creeks not be restricted, since coho run there from late July to early September.29p.3
Not public No public source says which activities would be allowed on the new HLB easement. That depends on HLB's easement terms and the Municipality's rules for the land. GBOS supervisor Brian Burnett suggested the corridor could support more trails.11 Neighbors and the Trails Committee chair worried it would damage the primitive character of the Lower Virgin Creek and Joe Danich trails.4,9▸1:05:47▸1:38:25 A former Trails Committee chair appears to say (the transcript is garbled here) that the trail from Virgin Creek to Ruane was set aside for non-motorized use.9▸1:30:37
How often would Enstar run snowmachines on the gas line corridor? Could anyone else?
Documented At the meeting, Enstar said it does leak surveys about every four years. Its engineer expected those to be done on foot, possibly by snowmachine in winter once the ground firms up, but "likely on foot" because the line is short.9▸1:02:23▸1:03:30 The meeting minutes instead say "annually, probably on foot."28 Enstar's written answer only says surveys follow PHMSA's schedule.27 Either way, that means a visit once every one to four years, probably on foot. Construction is another matter: wetland sections would use construction mats under the equipment.9▸57:30
Documented On other people's snowmachines: a commenter asked DNR to limit future mechanical access. DNR declined and said "the section line easement does not preclude motorized use as a public highway."29p.15 Not public Whether Municipal or HLB rules restrict motorized use on the new HLB easement or the surrounding open space is a separate question with no public answer yet. Ask HLB.
How much construction traffic on Timberline Drive and Virgin Creek Road, and for how long?
Documented The 2023 application planned about 3–4 weeks of construction (late July/early August to late August/early September), with access from Ruane Road on the west and Virgin Creek Road on the east. About 11 workers would be on site: 4 from Enstar, 4 from the drilling contractor, 2 tree clearers and possibly 1 excavating operator.25p.6 The equipment listed:
| Equipment | Gross weight (lb) |
|---|---|
| Vermeer directional drill | 60,000 |
| 200-class excavator | 50,000 |
| Vac truck | 50,000 |
| Reclaimer | 45,000 |
| Mud truck | 35,000 |
| F650/750 crew truck | 28,000 |
| Cat 308 and Cat 305 mini excavators | 20,077 and 12,688 |
| Two skid steers | 12,000 each |
| Two ¾- or 1-ton trucks | 10,000 each |
Tracked equipment would be stored along the alignment. Wheeled equipment would leave the site daily, and refueling would be from trucks on the road system.25p.6 Estimate Most of the drilling happens at the Glacier Creek crossing, reached from Ruane Road. The trenched section starts at the end of Virgin Creek Road. So Virgin Creek Road and Timberline would likely see a few heavy-equipment deliveries and pickups, plus daily trips by crew trucks and some wheeled equipment, for a few weeks. Not public No traffic estimate or schedule has been published for the current proposal. In 2024, Enstar said construction wouldn't happen that year.30 A neighbor said Virgin Creek Road already gets heavy traffic from visitors going to the falls.9▸1:53:45
What has Enstar done about bedrock, boulders and old-growth trees that could cause delays?
Documented Enstar said it would pick the tie-in point after boring and soil analysis.3 Its permits only let it build in the alignment it applied for, so any change, including for constructability, means reapplying.9▸1:12:59 A neighbor told GBOS the route on the bench runs through a boulder field that probably extends well below the surface.9▸1:08:48 In 2023, the only on-the-ground work residents had seen was by surveyors.9▸1:12:37
Commenters raised shallow bedrock and difficult terrain with DNR. DNR said it doesn't require subsurface investigations with an application, and that Enstar's design and terminus information was enough for its limited decision.29p.6 Enstar's design calls for 4 feet of cover over trenched pipe. The Glacier Creek bore would be at least 10 feet below the streambed, with the drill rig set 200 feet back from the high-water line.25p.2 Since then, Enstar has concluded it doesn't need to cross Virgin Creek, which removes one of the two bores.29p.1
Not public No geotechnical report or contingency plan for this project is public. For comparison, Enstar's 2026 Rabbit Creek reroute in Anchorage was delayed by drill rig delivery and a contractor change. Its fallback was to pull the pipe and redesign over the winter if the drilling couldn't be done.19
How many trees would be cut? Would the corridor be replanted or kept clear?
Not public No tree count has been published, for old-growth trees or any others.
Documented The 2023 plan cleared 3,350 feet × 20 feet, starting at the end of Virgin Creek Road and heading west. The 1,650 feet that would be drilled (Glacier Creek and its wetlands) weren't to be cleared, apart from the drill pits.25p.5
Estimate The areas involved:
The trees could be counted directly: walk the staked centerline and count the stems over a set diameter within 10 feet either side. Neighbors described trees "hundreds of years old" along the route.9▸1:31:35
Documented Revegetation plan from the application: cleared trees are mulched and spread along the strip. The trench (2 ft wide, 4 ft deep) is backfilled to the original grade, with topsoil on top as "a seed bed for native species." Seed is native to the site first, then the area, then the state. A DEC stormwater plan applies.25p.5 At the meeting, Enstar said it would clear about 15 feet, "maybe up to 20," mulch and chip on site, and reseed. A third-party inspector would check soil stabilization for the state DEC permit.9▸1:03:01▸53:38 But Enstar also wrote that federal pipeline-safety (PHMSA) rules require a cleared right-of-way for leak surveys and signs, so it asked to clear 20 feet for the full length.3 Its engineer expected alders to grow back.9▸1:04:17 In other words, the corridor would grow back as brush, not forest, and would be kept passable for people on foot doing surveys. Nothing in the record says it must be passable to vehicles. Enstar offered to meet neighbors about revegetation near their homes.3


Enstar on clearing and reseeding (1:02:54) · why 15–20 ft (1:28:43)
Limitations
- The HLB staff report for Resolution 2026-11 wasn't available. HLB said the Nov 19 packet would be posted Nov 13, but it couldn't be retrieved, so this page lacks its agency comments, its conditions and Enstar's reasons for the change. The easement's alignment comes from its legal description in the GBOS Nov 16 packet. It will likely answer several questions above. Read it before testifying.
- The residents' appeal itself wasn't reviewed. DNR's decision, Enstar's application and the 2023 GBOS materials come from copies that the Municipality's Girdwood staff sent to GBOS on Nov 13, 2026. Several are scanned and were read through OCR, so check the copies linked below before quoting.
- The appeal decision itself wasn't reviewed. DNR's online case file records that the Commissioner denied the appeal on June 18, 2025, but the decision document and its reasoning weren't found. The Land Use Committee was told in May 2026 that DNR hadn't responded, which conflicts with DNR's record.
- Meeting quotes come from machine transcripts (Open Minutes), which mishear names and words and sometimes misattribute speakers. Each link jumps to that moment in the video, so you can check.
- Estimates are the author's, not Enstar's, and are only meant to give a sense of scale.
- The 2023 plan may have changed. Much of the detail here (lengths, equipment, schedule) comes from Enstar's May 2023 application. Enstar has since dropped the Virgin Creek crossing, and the HLB easement reroutes the east end. The current design hasn't been published.
- Sources not checked: RCA filings for project-specific costs. Enstar's internal engineering, route-comparison or geotechnical studies (none are known to be public). Recordings of the Land Use Committee meetings (not in Open Minutes). The Nov 9, 2026 Land Use Committee meeting (its documents failed to load). HLBAC meeting recordings. Municipal rules on motorized use of HLB land. The Girdwood Trails Plan's specific designations for these trails. Any Enstar outreach since 2024. PHMSA data specific to Enstar.
Sources
"Archive" links are Wayback Machine snapshots. "Copy" links are copies of public government documents kept on this site in case the original moves.
- Heritage Land Bank. Public Hearing Notice, HLBAC Resolution 2026-11 (Enstar, Parcel 6-062). Posted Nov 5, 2026.
Original · Copy - Heritage Land Bank Advisory Commission. Agenda, November 19, 2026.
Original · Copy - Enstar (Steve Cooper). Letter to GBOS and DNR re ADL 234206, Aug 3, 2023.
Original (removed from muni.org in its Nov 2026 redesign) · Archive · Copy - Girdwood Board of Supervisors. Letter of Objection: ADL 234206, July 19, 2023.
Original (removed from muni.org in its Nov 2026 redesign) · Archive · Copy - Turnagain News. “Plan for gas line sparks heated reaction,” Jul 30, 2023.
Original · Archive - Turnagain News. “Enstar agrees to further review controversial gas line plan,” Aug 15, 2023.
Original · Archive - Turnagain News. “State OKs Gas Line through Virgin Creek Forest,” Sep 6, 2024.
Original · Archive - Turnagain News. “Girdwood Board reverses stance on Gas Line,” Sep 18, 2024.
Original · Archive - GBOS regular meeting, July 17, 2023 (Enstar item starts 43:03). Machine transcript on Open Minutes; video on YouTube; transcript excerpt copy.
Original · Video · Copy - GBOS special meeting, Sept 13, 2024. Machine transcript on Open Minutes; video on YouTube; transcript copy.
Original · Video · Copy - GBOS. Minutes, special meeting Sept 13, 2024.
Original (removed from muni.org in its Nov 2026 redesign) · Archive · Copy - Girdwood Land Use Committee. Minutes, Sept 9, 2024.
Original (removed from muni.org in its Nov 2026 redesign) · no archived copy found - Girdwood Land Use Committee. Minutes, May 11, 2026.
Original (removed from muni.org in its Nov 2026 redesign) · no archived copy found - GBOS. Meeting packet, Nov 16, 2026.
Original · Copy - HLBAC. Meeting packet, March 26, 2026 (a staff report citing AMC 25.40.025: HLBAC holds a hearing before recommending a disposal to the Mayor and Assembly).
Original · Copy - Turnagain News (Chase Berenson). “Whittier natural gas shutdown shows vulnerability of communities outside the Anchorage bowl,” Sep 1, 2026.
Original · Archive - Anchorage Daily News. “Triggering a 3-week outage, Enstar shuts off gas to Whittier for pipeline repairs,” Aug 17, 2026.
Original · Archive - Alaska Public Media / KTOO. “Whittier gas restored after Enstar secures temporary LNG supply,” Aug 26, 2026.
Original · Archive - Enstar. “2026 Rabbit Creek Gas Line Re-route” project page.
Original · Archive - PHMSA. National Pipeline Performance Measures.
Original · Archive - Radio Kenai. “ENSTAR Clarifies Rate Hike Impact as Southcentral Faces a Shrinking Gas Supply,” 2025.
Original · Archive - Alaska DNR, Division of Mining, Land and Water. Title information (section-line easements).
Original · Archive - Alaska DNR. Public Notice, ADL 234206, July 6, 2023.
Original · Copy - Alaska DNR. Agency Review Notice, comment period extended to Aug 3, 2023 (July 19, 2023), with application attached.
Copy · not found posted online; from documents Girdwood staff sent GBOS on Nov 13, 2026 - Enstar. Application for Easement ADL 234206 (redacted), development narrative and construction drawings “Girdwood Townsite Reinforcement,” May 2023.
Copy · not found posted online; from documents Girdwood staff sent GBOS on Nov 13, 2026 - Alaska DNR (Yannick Calvez). Public-notice map, ADL 234206, June 30, 2023.
Copy · not found posted online; from documents Girdwood staff sent GBOS on Nov 13, 2026 - Enstar. “ADL 234206 – Response to Request for Project Information,” answers to GBOS questions, July 2023.
Copy · not found posted online; from documents Girdwood staff sent GBOS on Nov 13, 2026 - GBOS. Minutes, regular meeting July 17, 2023 (converted from the original .doc).
Copy · not found posted online; from documents Girdwood staff sent GBOS on Nov 13, 2026 - Alaska DNR, Southcentral Regional Land Office (Jay Rokos). ADL 234206 decision: non-objection to developing the section-line easement, with public-comment responses. Signed Aug 26, 2024. 21 pages.
Copy · not found posted online; from documents Girdwood staff sent GBOS on Nov 13, 2026 - Enstar status update relayed by GBOS (Briana Sullivan) to Girdwood staff, Sept 9, 2024.
Copy · not found posted online; from documents Girdwood staff sent GBOS on Nov 13, 2026 - “Enstar similar photos,” July 2023 GBOS materials.
Copy · not found posted online; from documents Girdwood staff sent GBOS on Nov 13, 2026 - GBOS. Agenda, regular meeting Nov 16, 2026 (draft, rev. Nov 13, 2026).
Original · Copy - Alaska DNR, Land Administration System. Case File Abstract, ADL 234206 (case actions through the June 20, 2025 approval), as of Nov 17, 2026.
Original · Copy